Estimated Construction Completion: Early 2025
Estimated Settlement: Early 2025
We wish to advise that building work continues to progress well.
Click here to view Hyegrove Willoughby construction timeline and 360-degree views.
Please see the construction update for the past quarter below:
Milestones:
- Piling Complete
- Capping Beams Complete
- Shotcreting and Temp Anchors – 100% Complete
- Approx. 100,000m³ of soil removed off site
- Detail Excavation is 50% completed
- Crane 01 has been erected
- Pad footings on Level 2 basement on the East Side of the site have been poured
- Inground services have commenced
- Main Sewer is installed
Works planned on site for the first quarter of 2023:
- Erection of Crane 02
- Continuation of pouring basement slabs on ground
- Installation of Footings and Pad Footings
- Completion of Bulk Excavation
- Erection of first suspended slabs
Programme
The key programme items are as follows:
- Site set up works – Completed
- Demolition – Completed
- Shoring Works – In Progress
- Bulk Earthworks – In Progress
- Detailed Excavation – In Progress
- Basement works – In Progress
- Structure works – Not Started
- Services rough in – Not Started
- Window glazing – Not Started
- Facade cladding – Not Started
- Internal fit out works – Not Started
- Club Works – Not Started
- Finishing works – Not Started
- Landscaping – Not started
- Title registration – Not started
- Ready to settle –