Construction Update – Hyegrove

Estimated Construction Completion: February 2025
Estimated Settlement: March 2025

We wish to advise that building work continues to progress well.

Click here to view Hyegrove Willoughby construction timeline and 360-degree views.

Please see the construction update for the past quarter below:

Milestones:

  • Piling Complete
  • Capping Beams Complete
  • Shotcreting and Temp Anchors – 60% Complete
  • Approx. 65,000 m3 of soil removed off site
  • Detail Excavation has commenced
  • Crane 01 base has been poured
  • Pad footings on Level 2 basement on the East Side of the site have been poured
  • Inground services have commenced
  • Main Sewer is installed

Works planned on site for the first quarter of 2023:

  • Completion of bulk excavation to basement 2 & 3 working levels
  • Detailed Excavation to be completed under buildings A, B, C, D
  • Pad footing, Lift Pits to be poured on L3 basement under buildings A, B, C, D
  • Commencement of pouring basement slabs on ground L2
  • Installation of bracing and walers
  • Commencement of erecting columns and suspended slabs under buildings C & B
  • Completion of Anchor installation and shotcreting in the basement around buildings E & F

Programme

The key programme items are as follows:

  1. Site set up works – Completed
  2. Demolition – Completed
  3. Shoring Works – In Progress
  4. Bulk Earthworks – In Progress
  5. Detailed Excavation – In Progress
  6. Basement works – In Progress
  7. Structure works – Not Started
  8. Services rough in – Not Started
  9. Window glazing – Not Started
  10. Facade cladding – Not Started
  11. Internal fit out works – Not Started
  12. Club Works – Not Started
  13. Finishing works – Not Started
  14. Landscaping – Not started
  15. Title registration – Not started
  16. Ready to settle –