Estimated Construction Completion: February 2025
Estimated Settlement: March 2025
We wish to advise that building work continues to progress well.
Click here to view Hyegrove Willoughby construction timeline and 360-degree views.
Please see the construction update for the past quarter below:
Milestones:
- Piling Complete
- Capping Beams Complete
- Shotcreting and Temp Anchors – 60% Complete
- Approx. 65,000 m3 of soil removed off site
- Detail Excavation has commenced
- Crane 01 base has been poured
- Pad footings on Level 2 basement on the East Side of the site have been poured
- Inground services have commenced
- Main Sewer is installed
Works planned on site for the first quarter of 2023:
- Completion of bulk excavation to basement 2 & 3 working levels
- Detailed Excavation to be completed under buildings A, B, C, D
- Pad footing, Lift Pits to be poured on L3 basement under buildings A, B, C, D
- Commencement of pouring basement slabs on ground L2
- Installation of bracing and walers
- Commencement of erecting columns and suspended slabs under buildings C & B
- Completion of Anchor installation and shotcreting in the basement around buildings E & F
Programme
The key programme items are as follows:
- Site set up works – Completed
- Demolition – Completed
- Shoring Works – In Progress
- Bulk Earthworks – In Progress
- Detailed Excavation – In Progress
- Basement works – In Progress
- Structure works – Not Started
- Services rough in – Not Started
- Window glazing – Not Started
- Facade cladding – Not Started
- Internal fit out works – Not Started
- Club Works – Not Started
- Finishing works – Not Started
- Landscaping – Not started
- Title registration – Not started
- Ready to settle –