Construction Update – Hyegrove

Estimated Construction Completion: February 2025
Estimated Settlement: March 2025

We wish to advise that building work continues to progress well.

Click here to view Hyegrove Willoughby construction timeline and 360-degree views.

Please see the construction update for the past quarter below:

Milestones:

  • 150 Piles have been installed
  • 50% of the capping beam installed
  • Approx. 30,000 m³ of material removed off site
  • Installation of concreting and anchors have commenced

Works planned on site for the first quarter of 2023:

  • Completion of all piling
  • Completion of form, reo & pour of the capping beams
  • Completion of Bulk Excavation
  • Completion Shoring (shotcreting & anchors)
  • Commencement of detail excavation
  • Commencement of Form, reo and pour of footings under the bottom basement slab
  • Completion of sewer redirection works onsite
  • Commencement of inground services
  • Erection of Crane 1 of 2

Programme

The key programme items are as follows:

  1. Site set up works – Completed
  2. Demolition – Completed
  3. Shoring Works – In Progress
  4. Bulk Earthworks – In Progress
  5. Detailed Excavation – Not Started
  6. Basement works – Not Started
  7. Structure works – Not Started
  8. Services rough in – Not Started
  9. Window glazing – Not Started
  10. Facade cladding – Not Started
  11. Internal fit out works – Not Started
  12. Club Works – Not Started
  13. Finishing works – Not Started
  14. Landscaping – Not started
  15. Title registration – Not started
  16. Ready to settle –