Construction Update – Hyegrove

Estimated Construction Completion: Early 2025
Estimated Settlement: Early 2025

Click here  to view a timeline of the build go to our 360 photo captured in July 2024

We wish to advise that building work continues to progress well.

Please see the construction update below:

Milestones:

  • Basement 02 & 03 – Blockwork wall construction complete
  • Basement 03 – High-Level Services rough-ins complete
  • Basement 02 & 03 – Soffits & Columns painting complete
  • Basement 02 & 03 – Soffit Insulation Complete
  • Building C – internal wall sheeting, windows, waterproofing complete. Tiling and joinery installation underway.
  • Building B – internal wall sheeting and windows complete. Waterproofing, tiling and joinery installation underway.
  • Building D – above ceiling services rough-ins, internal and external wall framing and window prep complete.
  • Building A – Structure complete, above ceiling services roughins, internal and external wall framing complete. Wall sheeting up to Level 2.
  • Building E – Structure complete and stripping of formwork materials underway. above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep to commence up to Level 2
  • Building F (Club Willougby) – Structure up to Roof Level.
  • Façade & Scaffold Stripping to Buildings C

Works planned on site for the third quarter of 2024:

  • Basement 01 – Blockwork wall construction complete
  • Basement 02 – High-Level Services rough-ins complete
  • Basement 01 – Soffits & Columns painting complete
  • Basement 01 – Soffit Insulation Complete
  • Building C – final fit off and lock-up to Units.
  • Building B – final fit off and lock-up to Units up to Level 3.
  • Building D – above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep complete.
  • Building A – internal wall sheeting, windows, waterproofing, tiling
    and joinery installation complete up to Level 4.
  • Building E – above ceiling services rough-ins, internal and external wall framing and window prep complete.
  • Building F (Club Willougby) – Structure Complete, above ceiling services rough-ins, internal and external wall framing, waterproofing, and window  prep to commence up to Level 2
  • Façade & Scaffold Stripping to Buildings B & D

Programme

The key programme items are as follows:
  • Site set up works Completed
  • Demolition Completed
  • Shoring Works Completed
  • Bulk Earthworks Completed
  • Detailed Excavation Completed
  • Basement works Completed
  • Structure works In Progress
  • Services rough in In Progress
  • Window glazing In Progress
  • Facade cladding In Progress
  • Internal fit-out works In Progress
  • Club Works Not Started
  • Finishing works Not Started
  • Landscaping Not Started
  • Title registration Not Started
  • Ready to settle –

Next Update: January 2025