Estimated Construction Completion: Early 2025
Estimated Settlement: Early 2025
Click here to view a timeline of the build go to our 360 photo captured in July 2024
We wish to advise that building work continues to progress well.
Please see the construction update below:
Milestones:
- Basement 02 & 03 – Blockwork wall construction complete
- Basement 03 – High-Level Services rough-ins complete
- Basement 02 & 03 – Soffits & Columns painting complete
- Basement 02 & 03 – Soffit Insulation Complete
- Building C – internal wall sheeting, windows, waterproofing complete. Tiling and joinery installation underway.
- Building B – internal wall sheeting and windows complete. Waterproofing, tiling and joinery installation underway.
- Building D – above ceiling services rough-ins, internal and external wall framing and window prep complete.
- Building A – Structure complete, above ceiling services roughins, internal and external wall framing complete. Wall sheeting up to Level 2.
- Building E – Structure complete and stripping of formwork materials underway. above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep to commence up to Level 2
- Building F (Club Willougby) – Structure up to Roof Level.
- Façade & Scaffold Stripping to Buildings C
Works planned on site for the third quarter of 2024:
- Basement 01 – Blockwork wall construction complete
- Basement 02 – High-Level Services rough-ins complete
- Basement 01 – Soffits & Columns painting complete
- Basement 01 – Soffit Insulation Complete
- Building C – final fit off and lock-up to Units.
- Building B – final fit off and lock-up to Units up to Level 3.
- Building D – above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep complete.
- Building A – internal wall sheeting, windows, waterproofing, tiling
and joinery installation complete up to Level 4. - Building E – above ceiling services rough-ins, internal and external wall framing and window prep complete.
- Building F (Club Willougby) – Structure Complete, above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep to commence up to Level 2
- Façade & Scaffold Stripping to Buildings B & D
Programme
The key programme items are as follows:
- Site set up works Completed
- Demolition Completed
- Shoring Works Completed
- Bulk Earthworks Completed
- Detailed Excavation Completed
- Basement works Completed
- Structure works In Progress
- Services rough in In Progress
- Window glazing In Progress
- Facade cladding In Progress
- Internal fit-out works In Progress
- Club Works Not Started
- Finishing works Not Started
- Landscaping Not Started
- Title registration Not Started
- Ready to settle –
Next Update: January 2025