Construction Update – Hyegrove

Estimated Construction Completion: Early 2025
Estimated Settlement: Early 2025

Click here  to view a timeline of the build go to our 360 photo captured in December 2023

We wish to advise that building work continues to progress well.

Please see the construction update below:

Milestones:

  • Inground services complete
  • OSD tank slab and walls poured
  • OSD pump out pit and sewer tank installed
  • 100% of all slabs on the ground basement 03 have been poured
  • 100% of basement 02 concrete slabs have been poured
  • 100% of level 1 podium have been poured
  • Building C – Structure Complete
  • Building B – Structure Complete
  • Ramps between basement 02 to Level 1 are completed

Works planned on site for the second quarter of 2024:

  • 100% Basement 01 concrete slabs to be poured
  • 100% Podium levels to be poured
  • Building A – Structure to Level 5 Poured.
  • Building D – Structure Complete
  • Building E – Structure to Levels 1, 2,3 & 4 Complete.
  • Building F – Structure to Level 1, 2 & 3 Complete.
  • Basement 02 & 03 – Blockwork wall construction complete
  • Basement 03 – High-Level Services rough-ins complete
  • Basement 02 – High-Level Services rough-ins complete
  • Lift delivery
  • Basement Soffits & Columns painting completed
  • Basement Soffit Insulation to have commenced
  • Building C – above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep complete.
  • Building B – above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep complete
  • Building A – Levels 2 & 3 above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep to commence.

Programme

The key programme items are as follows:
  • Site set up works Completed
  • Demolition Completed
  • Shoring Works Completed
  • Bulk Earthworks Completed
  • Detailed Excavation Completed
  • Basement works Completed
  • Structure works In Progress
  • Services rough in In Progress
  • Window glazing In Progress
  • Facade cladding In Progress
  • Internal fit-out works In Progress
  • Club Works Not Started
  • Finishing works Not Started
  • Landscaping Not Started
  • Title registration Not Started
  • Ready to settle –

Next Update: July 2024