Construction Update – Hyegrove

Estimated Construction Completion: Early 2025
Estimated Settlement: Early 2025

Milestones:

  • Bulk & detailed earthworks complete
  • Shoring complete
  • Cranes 01 & 02 erected
  • Concrete Tower Boom erected
  • All pad footings & lift pits poured
  • Inground services complete
  • OSD tank slab and walls poured
  • OSD pump out pit and sewer tank installed
  • 100% of all slabs on the ground basement 03 have been poured
  • 100% of basement 02 concrete slabs have been poured
  • 60% of level 1 podium have been poured
  • 85% of level 1 podium formwork have been erected
  • Building C – levels 2 & 3 formed and poured
  • Building B – level 2 formwork commenced
  • Scaffold to building B up to level 03 erected, Scaffold to building C up to level 4 erected.
  • Ramps between basement 02 to Level 1 are completed

Works planned on site for the first quarter of 2024:

  • 100% Basement 01 concrete slabs to be poured
  • 100% Podium levels to be poured
  • Building C – structure to be completed
  • Building B – structure to be completed
  • Building A – Levels 2, 3 & 4 to be poured. Level 5 formed
  • Building D – Levels 2 & 3 to be poured & Level 4 formed
  • Building E – Levels 2 & 3 to formed
  • Building F – Level 1 to be poured and level 2 to be formed
  • Basement 02 & 03 – Blockwork wall construction commenced
  • Basement 03 – High-Level Services rough-ins complete
  • Basement 02 – High-Level Services rough-ins commenced
  • Lift delivery
  • Basement Soffits & Columns painting completed
  • Basement Soffit Insulation to have commenced
  • Building C – above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep to commence
  • Building B – above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep to commence
  • Building A – Levels 2 & 3 above ceiling services rough-ins, internal and external wall framing, waterproofing, and window prep to commence

Programme

The key programme items are as follows:
  • Site set up works Completed
  • Demolition Completed
  • Shoring Works Completed
  • Bulk Earthworks Completed
  • Detailed Excavation Completed
  • Basement works In Progress
  • Structure works In Progress
  • Services rough in In Progress
  • Window glazing In Progress
  • Facade cladding In Progress
  • Internal fit-out works In Progress
  • Club Works Not Started
  • Finishing works Not Started
  • Landscaping Not Started
  • Title registration Not Started
  • Ready to settle –